Haveli Establishes New Gas Turbine Installation Record
NPPMCL achieved First Fire milestone of 2nd Gas Turbine at Haveli Bahadur Shah today at 12:06pm.
It took exactly 73 days from Gas Turbine’s arrival at site to First Fire, which is 21 days less than own record of fastest installation time ever achieved for a 9HA.01 (94 days First Fire of 1st Gas Turbine at Haveli) .
This new record is exactly half the time taken by GE itself (146 days) for this machine in co-development of EDF power plant in Bouchain, France.